Indiana Court of Appeals holds that a contractor’s failure to comply with the Home Improvement Contracts Act did not prevent its claim for unjust enrichment and on its mechanic’s lien.
In Kevin Walsh v. Chris Sweeney Construction, Inc., the Indiana Court of Appeals denied a homeowner’s argument that a contractor’s failure to comply with the Home Improvements Contact Act (“HICA”) should preclude the contractor from recovering for its unpaid work on the theory of unjust enrichment and on its mechanic’s lien.
Facts: Chris Sweeney Construction, Inc. (“CSCI”) provided a quote to Kevin Walsh to perform various remodeling work on his home. Walsh agreed to the price, and CSCI performed the work—but it did not execute a written contract. When a dispute arose over the work, CSCI recorded a mechanic’s lien on the property for $4,150 in unpaid work.
HICA generally requires a home improvement contractor to provide a consumer with a written home improvement contract containing certain provisions. At the bench trial, CSCI only pursued claims on its mechanic’s lien and unjust enrichment, knowing that it would not be able to prevail on its breach of contract claim because of its failure to comply with HICA. Walsh filed a counterclaim based on CSCI’s violation of HICA.
The trial court held that CSCI was entitled to the unpaid amount plus its attorney’s fees (under Indiana mechanic’s lien act). Walsh appealed and argued that because HICA prevented a breach of contract claim, CSC should also be precluded from recovering on a theory of unjust enrichment or under the mechanic’s lien.
Decision: The Indiana Court of Appeals affirmed the trial court’s decision. In the absence of a contract, a party may recover under a theory of unjust enrichment—an equitable doctrine that permits recovery when the circumstances are such that justice requires recovery as though there has been a promise. A mechanic’s lien is equitable in nature and is based upon a theory of unjust enrichment. The Appellate Court found that it would be unjust for Walsh to retain the benefit of CSCI’s services despite CSCI’s non-compliance with HICA.
Walsh also lost on his counterclaim for violating HICA. HICA provides that a supplier’s failure to give the consumer a written contract is a deceptive act. However, to establish entitlement to those remedies, the homeowner must show that the deceptive act was either uncured, meaning that notice was given and the deceptive act was not cured, or incurable, meaning that the supplier acted with intent to defraud or mislead the consumer. Walsh offered no evidence that he notified CSCI of its deceptive act or offered it the opportunity to cure the deceptive act. The Court also found that CSCI’s deceptive act was not willful or intentional and that it was not part of a scheme, artifice, or device intended to defraud or mislead Walsh.
The Walsh case is “unpublished,” which means that it cannot be regarded as precedent for other cases; but it likely illuminates the Court’s approach to a contractor’s non-compliance with HICA if there is no evidence of intent to defraud or mislead. Nevertheless, home improvement contractors should ensure that their contracts comply with Indiana law.
By: Roy Rodabaugh
Our construction litigation team consists of Roy, Mike Cavosie, and Theresa Ringle.
Indiana Court of Appeals affirms judgment against contractor and surety on differing site conditions claim.
In Dave’s Excavating, Inc. and Liberty Mutual Insurance Co. v. City of New Castle, Indiana, the Indiana Court of Appeals affirmed a $900,000 judgment against a contractor and surety arising out of the contractor’s differing site conditions claim. The decision is a cautionary tale warning that a contractor’s refusal to perform disputed work may have catastrophic consequences.
Read more →
Reminder: Accrued vacation time must be paid at termination absent a written policy to the contrary.
Today’s Indiana Court of Appeals decision in Shofstall v. International Union of Painters and Allied Trades is a reminder that accrued vacation time must be paid at termination unless the employer has adopted a written policy to the contrary. Such policies are often included in employee handbooks and can preclude payment of vacation time upon termination or otherwise condition payment upon a contingency such as providing and working through a two-week notice.
Indiana Court of Appeals holds that no-waiver contract clause negates argument that change order time limitations were waived.
In Boyer Corp. Excavating v. Shook Construction and Ball State University Board of Trustees, the Indiana Court of Appeals denied Boyer Corp.’s argument that Shook Construction had waived the right to enforce a “Time Limits on Claims” clause.
Read more →
Tippecanoe County Circuit Court interprets Indiana’s new local preference statute.
The Tippecanoe County Circuit Court recently rejected a contractor’s argument that, as a local Indiana business, it should have been awarded a project even though it was not the lowest bidder.
Read more →
Theresa Ringle and Mike Cavosie seminar in South Bend
On January 26, 2012, Theresa Ringle and Mike Cavosie will present a seminar entitled “Legal Issues for Professional Engineers.”
Read more →
Welcome to the new Easter & Cavosie website
Acquaint yourself with our practice and our people. Track relevant construction, real estate, and design law updates in this space, or sign up for periodic email alerts. We look forward to working with you.
